Renaissance GroupA Super Structures company
Running the Job

Submittals, RFIs & Documentation

Submittals, RFIs & Documentation
dalbera · CC BY · Openverse

Submittals, RFIs & Documentation

Most disputes are won or lost on documentation. Two core processes keep a job clear.

Submittals

Before installing many products, the contractor sends submittals (product data, samples, shop drawings) to the architect/engineer for approval — confirming what's being installed matches the design. Don't order or install until approved.

RFIs (Requests for Information)

When the drawings are unclear or conflict, you send an RFI to get a written answer. RFIs create a record of the question and the official response.

The paper trail

Going Deeper (Intermediate)

Two documents keep a job correct and out of court:

Advanced / Pro-Level

Where PMs win or lose the schedule:

Practice Challenge

The switchgear has a 16-week lead time and the job is 20 weeks long. When must its submittal be approved, and what happens if you treat it like any other? (Answer: it must be submitted/approved in the first few weeks — it's effectively on the critical path; treat it as routine and the 16-week lead time stalls the entire project.)

In Practice

A sub installs a product before submittal approval — and it's the wrong one, so it gets torn out. Submittals and written RFIs prevent exactly that.

Common Mistakes to Avoid

Takeaway: Use submittals to confirm what's installed and RFIs to clarify the design — and document everything; the paper trail protects you.

Educational content — not legal or contractual advice. Follow your contract's specific procedures and deadlines.

Sign in to track your progress